Judicial/ Administrative Decisions

On March 12, 2018, the United States Court of Appeals for the Second Circuit affirmed a Federal Energy Regulatory Commission (FERC) order finding that delays by the New York Department of Environmental Conservation (NYDEC) in reviewing Millennium Pipeline Company’s application for water quality certification constituted waiver of NYDEC’s authority under the Clean Water Act (CWA). As we detailed in an earlier blog post, FERC found that NYDEC’s delay exceeded the one-year statutory period established by CWA Section 401. The Millennium case is just one of several interstate natural gas pipeline projects that have faced delays associated with the CWA Section 401 permitting process. (See, e.g., Atlantic Bridge Project, Atlantic Sunrise Project, Constitution Pipeline, Northern Access Project, PennEast Pipeline, and Spire STL Pipeline.) The Court’s decision resolves the nearly three-year permitting process for the Millennium Valley Lateral Pipeline and clarifies for other projects (and state agencies reviewing those projects) that the one-year waiver period begins when the state agency receives the initial request for certification. Continue Reading Second Circuit Affirms Waiver Period for State Water Quality Certification Begins Upon Receipt of Request for Certification

This week, the U.S. District Court for the Middle District of Louisiana granted a preliminary injunction, halting construction of the $750 million Bayou Bridge Pipeline. Judge Shelly D. Dick concluded that the U.S. Army Corps of Engineers, in authorizing the project, did not provide sufficient explanation for how the proposed off-site mitigation would compensate for the loss of wetlands impacted by construction. In addition, the Court found the Corps’ environmental analysis failed to sufficiently consider and address historical impacts to wetlands from similarly situated pipelines. Thus, the Court held that these deficiencies likely violated the National Environmental Policy Act (NEPA) and ordered the 162-mile oil pipeline to halt construction within the Atchafalaya Basin, a large wetland habitat for a variety of fish and wildlife species and a critical component of regulating flooding and stream recharge in the region. As we recently saw with the D.C. Circuit’s decision to vacate authorizations for the Sabal Trail Pipeline, this is another example of courts and environmental organizations relying on errors in a federal agency’s NEPA analysis to justify enjoining pipeline construction or operations. Continue Reading Federal District Court Halts Construction of Louisiana Pipeline Due to Corps’ Failure to Explain Off-Site Mitigation

Federal agencies that authorize or permit large infrastructure projects, like interstate natural gas pipelines, are often subject to the requirements of the National Environmental Policy Act (NEPA), and environmental organizations frequently rely on NEPA to challenge a project. The D.C. Circuit recently struck down a decision by the Federal Energy Regulatory Commission (FERC) to approve the construction and operation of three interstate natural gas pipelines because the Court found defects in FERC’s NEPA analysis. The court’s decision to vacate FERC’s authorization now threatens to shut down the pipelines, including the Sabal Trail pipeline currently supplying natural gas to newly constructed power plants in Florida.

See the full report on The Nickel Report blog.

On January 31, 2018, in proceedings to condemn easements for the Mountain Valley Pipeline project, the US District Court for the Western District of Virginia ruled that the pipeline company’s preliminary injunction motions for pretrial possession of the easements would be granted only if it appraised each of the nearly 300 properties at issue.

Continue Reading Virginia District Court Requires Pipeline Company to Obtain Appraisals Before Granting Preliminary Injunctions For Prejudgment Possession of Land

Once large infrastructure projects, such as oil and natural gas pipelines, receive federal government approval, they are often the target of legal challenges from opposition groups.  Opponents repeatedly argue that the environmental review, pursuant to the National Environmental Policy Act (NEPA), was insufficient. If a court finds deficiencies in the government’s NEPA analysis, can a court halt construction or cease operations even after years of project design, permit approvals at all levels of government, and tens of millions of dollars in investment? This question was at the heart of the ongoing litigation involving the controversial Dakota Access Pipeline (DAPL), and, on October 11, Judge James Boasberg determined “no,” the court would not shut down the pipeline. This case is important precedent for projects being challenged under NEPA. The same issue is at play in the Sabal Trail case currently under review by the US Court of Appeals for the DC Circuit.  See Sierra Club, et al. v. FERC, No. 16-1329 (D.C. Cir. filed Sept. 21, 2016).

Continue Reading Federal Judge Declines to Shut Down Dakota Access Pipeline While Corps Corrects Errors in Environmental Review

On September 15, 2017, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order in which it concluded that delays by the New York Department of Environmental Conservation (NYDEC or the Department) in processing Millennium Pipeline Company’s application for Clean Water Act (CWA) water quality certification constituted a waiver of the certification requirement. The order resolves a lengthy saga regarding water quality certification for Millennium’s Valley Lateral Project. It reaffirms previous FERC precedent establishing that the one-year waiver period for CWA water quality certification decisions by state agencies begins when  the state agency receives a written application for certification, regardless of the state agency’s determination that the application is incomplete or requests for further information.

Continue Reading FERC: Water Quality Certification Waiver Period for Pipeline Projects Begins Upon Receipt of a Written Request for Certification

As previously reported on PipelineLaw, the ongoing controversy over an April 2016 decision by the New York Department of Environmental Conservation (NYDEC or the Department) to deny a Clean Water Act (CWA) water quality certification to Constitution Pipeline Company (Constitution or the Company) for its interstate natural gas pipeline project in Pennsylvania and New York highlights tensions between federal and state oversight of such projects. In the latest chapter of this controversy, the Second Circuit recently denied Constitution’s petition for review of the NYDEC decision, concluding that (1) the Court lacked jurisdiction over the Company’s claims to the extent that they challenged the timeliness of the decision; and (2) the Department acted within its statutory authority in denying the certification, and its denial was not arbitrary or capricious.

Continue Reading Second Circuit Upholds State Veto of Constitution Pipeline Project Via Denial of Water Quality Certification

Since the Administration denied a Presidential (border crossing) Permit to the Keystone XL Project in 2015, a number of regional, state or local objections to new pipeline construction projects have emerged around the U.S.  Most of the protests have continued themes relied on by opposition to Keystone, including the claim that fossil fuels should remain in the ground in order to limit the impacts of climate change.  Groups such as the Sierra Club and Earth Justice have acknowledged that they selected Keystone as a tangible subject to carry their climate change message, which is otherwise rather abstract.  Ironically, the Keystone and subsequent protests seem to focus on oil and gas as more emblematic of fossil fuels than coal, and they ignore the significant safety advantages in transporting energy by pipeline as compared to any other method.  In addition, they ignore economic and safety factors that counsel in favor of new pipeline construction, and avoid discussion about the realistic availability of alternative energy resources provide a majority of U.S. demand in the near future.

Continue Reading Standing Rock Dispute Presents Issues Unique to Indian Country

The Third Circuit held in a highly anticipated recent decision that state actions on water quality-related permits for interstate natural gas pipeline projects are reviewable only in the federal Circuit Courts of Appeals, in accordance with the Natural Gas Act (NGA).  The case, Delaware Riverkeeper v. Secretary, Pennsylvania Department of Environmental Protection et al., concerned petitions for review filed by environmental and conservation groups in New Jersey and Pennsylvania to challenge state permitting decisions for the Transcontinental Pipeline (Transco) Leidy project.  Specifically, the groups challenged the decisions of the Pennsylvania and New Jersey Departments of Environmental Protection (PDEP and NJDEP, respectively) to issue water quality certifications under Section 401 of the Clean Water Act (CWA) and, in the case of the NJDEP, other water quality-related permits required under State law.

Continue Reading Federal Appellate Review of State Agency Decisions for Interstate Natural Gas Projects Confirmed

Recent developments in cases brought by Constitution Pipeline Company to challenge New York’s denial of certain water quality authorizations highlight tensions between federal and state oversight of interstate natural gas pipeline construction projects, and the accompanying potential for costly and protracted delays.  Under the scheme of “cooperative federalism” set up by many environmental statutes—such as the Clean Water Act (CWA), the Clean Air Act, and the Endangered Species Act—even where a natural gas project is under the exclusive federal regulatory jurisdiction of the Federal Energy Regulatory Commission (FERC), it will often require state-issued permits or other authorizations to go forward.  The controversy in the pending Constitution Pipeline cases concerns the extent to which a state may assert authority over discrete aspects of a federally-regulated project in a manner that delays or prevents its construction.

Continue Reading Constitution Pipeline Cases Reflect Tension in States’ Roles in Permitting Natural Gas Projects