Last week, the US District Courts for the Eleventh and Sixth Circuits joined a growing chorus of other circuits holding that a Natural Gas Act (NGA) condemnor can obtain immediate, pre-trial possession of condemned land through a preliminary injunction (PI) remedy so long as it demonstrates its substantive power of eminent domain as a FERC certificate holder under NGA § 7(h).[1] The Sixth Circuit’s ruling also rejected arguments that export-related aspects of a domestic pipeline project somehow negated a pipeline company’s public interest showing, required for obtaining a PI granting immediate possession. In addition, the two rulings address several commonly-arising procedural issues in a manner favorable to pipeline companies seeking immediate possession in NGA condemnations.