On March 12, 2018, the United States Court of Appeals for the Second Circuit affirmed a Federal Energy Regulatory Commission (FERC) order finding that delays by the New York Department of Environmental Conservation (NYDEC) in reviewing Millennium Pipeline Company’s application for water quality certification constituted waiver of NYDEC’s authority under the Clean Water Act (CWA). As we detailed in an earlier blog post, FERC found that NYDEC’s delay exceeded the one-year statutory period established by CWA Section 401. The Millennium case is just one of several interstate natural gas pipeline projects that have faced delays associated with the CWA Section 401 permitting process. (See, e.g., Atlantic Bridge Project, Atlantic Sunrise Project, Constitution Pipeline, Northern Access Project, PennEast Pipeline, and Spire STL Pipeline.) The Court’s decision resolves the nearly three-year permitting process for the Millennium Valley Lateral Pipeline and clarifies for other projects (and state agencies reviewing those projects) that the one-year waiver period begins when the state agency receives the initial request for certification.
Continue Reading Second Circuit Affirms Waiver Period for State Water Quality Certification Begins Upon Receipt of Request for Certification