On July 6, the US District Court for the District of Columbia found that the Dakota Access Pipeline (DAPL) must shut down while the US Army Corps of Engineers (Corps) prepares an Environmental Impact Statement (EIS) in accordance with the National Environmental Policy Act (NEPA).
Continue Reading Dakota Access Pipeline Must Shutdown While Corps Prepares Environmental Impact Statement

As we highlighted in our March 2, 2018, post, the US District Court for the Middle District of Louisiana ordered the $750 million Bayou Bridge pipeline to halt construction within the Atchafalaya Basin when it concluded that the US Army Corps of Engineers’ environmental analysis likely violated the National Environmental Policy Act (NEPA) and the Clean Water Act (CWA) due to the following deficiencies:

  • The Corps did not provide sufficient explanation for how the proposed off-site mitigation would compensate for the loss of wetlands impacted by construction; and
  • The Corps failed to sufficiently consider and address historical impacts to wetlands from past pipeline projects in the cumulative effects analysis.


Continue Reading Fifth Circuit Vacates Preliminary Injunction on Appeal, Allowing Bayou Bridge Pipeline to Proceed

Once large infrastructure projects, such as oil and natural gas pipelines, receive federal government approval, they are often the target of legal challenges from opposition groups. Opponents repeatedly argue that the environmental review, pursuant to the National Environmental Policy Act (NEPA), was insufficient. If a court finds deficiencies in the government’s NEPA analysis, can a court halt construction or cease operations even after years of project design, permit approvals at all levels of government, and tens of millions of dollars in investment? This question was at the heart of the ongoing litigation involving the controversial Dakota Access Pipeline (DAPL), and, on October 11, Judge James Boasberg determined “no,” the court would not shut down the pipeline. This case is important precedent for projects being challenged under NEPA.
Continue Reading Federal Judge Declines to Shut Down Dakota Access Pipeline While Corps Corrects Errors in Environmental Review

Despite oil already flowing through the pipeline, federal litigation involving the controversial Dakota Access Pipeline (DAPL) took another turn last week when partial summary judgment was granted to tribes challenging the adequacy of the US Army Corps of Engineers’ review of DAPL under the National Environmental Policy Act (NEPA) and other statutes. Two tribes, the Standing Rock Sioux Tribe and the Cheyenne River Sioux Tribe, filed suit in July 2016 attempting to block construction of the last remaining segment and operation of DAPL. As sometimes is the case, agency approvals came faster than the court’s opinion, and without a stay of proceedings DAPL began operating in early June 2017. Having granted partial summary judgment, the court did not require pipeline operations to cease, instead delaying the question of an appropriate remedy until after further briefing by the parties.
Continue Reading Federal Court Remands Corps Environmental Analysis for Dakota Access Pipeline

On September 29, 2015, the D.C. Circuit Court of Appeals ruled that the National Environmental Policy Act (NEPA) did not require federal agencies authorizing portions of an interstate oil pipeline project to conduct a “whole-pipeline” environmental review.
Continue Reading D.C. Circuit Rules that NEPA Does Not Require “Whole-Pipeline” Review for Oil Pipelines