On March 12, 2018, the United States Court of Appeals for the Second Circuit affirmed a Federal Energy Regulatory Commission (FERC) order finding that delays by the New York Department of Environmental Conservation (NYDEC) in reviewing Millennium Pipeline Company’s application for water quality certification constituted waiver of NYDEC’s authority under the Clean Water Act (CWA). As we detailed in an earlier blog post, FERC found that NYDEC’s delay exceeded the one-year statutory period established by CWA Section 401. The Millennium case is just one of several interstate natural gas pipeline projects that have faced delays associated with the CWA Section 401 permitting process. (See, e.g., Atlantic Bridge Project, Atlantic Sunrise Project, Constitution Pipeline, Northern Access Project, PennEast Pipeline, and Spire STL Pipeline.) The Court’s decision resolves the nearly three-year permitting process for the Millennium Valley Lateral Pipeline and clarifies for other projects (and state agencies reviewing those projects) that the one-year waiver period begins when the state agency receives the initial request for certification. Continue Reading Second Circuit Affirms Waiver Period for State Water Quality Certification Begins Upon Receipt of Request for Certification

On January 11, 2018, the Federal Energy Regulatory Commission (FERC) denied Constitution Pipeline Company, LLC’s Petition for a Declaratory Order that New York had waived its ability to act under section 401 of the Clean Water Act (CWA) by failing to grant or deny Constitution’s application for a section 401 certification within a “reasonable period of time.” See In re Constitution Pipeline Co., LLC, 162 FERC ¶ 61,014 (Jan. 11, 2018). The decision is another in a sequence of decisions from FERC and the federal courts of appeals concerning the time period for States to act under section 401.

Continue Reading FERC Rules on State Waiver of Section 401 Water Quality Certification